A job example


To enlarge images and text, hold [CTRL] + click [+/=] several times.
To shrink images and text, hold [CTRL] + click [-/_] several times.

Intro

This chapter gives a summary from the first idea to the complete wall. Then you can delve into later chapters giving more detail.

If you are practicing bricklaying, without wanting a permanent wall, follow these instructions but omit the cement from the mortar. The wall can then be easily pulled down, and the bricks cleaned of mortar. Remember that cement is a relatively recent invention. Old buildings did not use it.

In western countries where labor is expensive, building sites, on cleanup day, will sometimes give away offcuts of steel mesh, concrete blocks and bricks, scrap timber, and such. Make inquiries in advance; offer to help with the cleanup; and be there before anyone else.

Read thoroughly till you understand all aspects, before buying materials.
Laying bricks for small-to-medium jobs, is within the average handy person's ability. Large walls or home extensions require an engineer's specifications on architectural-style plans. While many untrained people successfully build houses, previous practice on small jobs is advisable to build confidence and reduce stress. [I worked as an offsider to several brickies (bricklayers) to pick up useful techniques which save time and avoid wastage.]

Contents

    Intro
1: Learning terms
2: Choose a bond
3: Get approval
4: Buying materials
5: Preparing the site
6: Foundations
7: Mortar
8: Laying bricks
9: Finishing
10: Cleaning up
11: Tools
12: Checklist
13: Tips

Step 1: Learning terms

1.gif not found
Bond: the pattern in which bricks are laid: Buttering: coating the end of the brick with mortar to form a vertical joint.
Course: a single row of bricks.
Footing: the subsoil upon which your foundation sits.
Foundation: the trench of concrete, mostly below ground, upon which your bricks will sit.
Joints: the mortar between bricks, usually 10mm thick.
Perpend: (perpend as in perpendicular) the vertical joint between bricks. Each perpend should be covered by a brick, that is, a perpend should not extend up 2 adjacent courses.
Piers: supporting columns built at regular intervals and at the end of high or long walls to give added strength.
Back to Contents

Step 2: Choose a bond

2.gif not found
The bricks are laid in patterns called bonds, which prevent one perpend being laid directly above a perpend of the course below. There are several different bonds, each one having its own appeal, and some more aesthetically pleasing, but this depends on the viewer's taste.
Stretcher bond is the simplest (Fig 2), in which bricks overlap by half their length. At each end of a wall, every second course finishes with half a brick.
Header bond lays bricks head on, with each course overlapping by half the header face width (Fig 2A). Every 2nd course finishes with 2 3/4 bricks laid next to each other at each end.
Back to Contents

Step 3: Get approval

3.gif not found
If you are planning a large structure, such as a high front brick wall, check the regulations of your local council of Shire. Most authorities in western countries specify the types of fences you can build and how high they can be, and you may need a permit. However, small edging walls, barbecues and such do not usually need a permit.

There is a big variation in the load-bearing capacity of soils, sometimes only a few metres apart. Do you know what your soil can carry ? Ask your local council.
Back to Contents

Step 4: Buying materials

4.gif not found
Bricks: The actual size in Australia is 230mm long x 110 deep x 76mm high. (110mm is too wide to be aesthetically pleasing for that length of 230mm, but it saves on labor.) Thus, with mortar, each brick face occupies 240 x 86mm. If you have a wall 8m long and 1.2m high, your brick needs are (8m/240mm) x (1.2m/86mm) + wastage. Wastage includes bricks accidentally broken or badly cut and rejected, and offcuts because the ends of some courses use only a portion of a brick. This comes to:
length = 8m/240mm = 33.33 bricks = 34 bricks long
height = 1.2m/86mm = 13.95 bricks = 14 bricks high
In both cases, adjust the thickness of mortar to avoid cutting bricks.

Total bricks = 34 x 14 = 476 + wastage (5% ?) = 500 bricks
Bricks come on pallets. Two pallets ordered at different times could have different shades of the color you ordered, so might look very different. If you intend to build another wall adjacent to this one, order enough bricks for both, to be delivered at the same time.

Mortar: For small jobs one bag of pre-mixed mortar lays 40-50 bricks. For larger jobs it is cheaper to mix your own. Cement and lime usually come in 40kg bags, and sand is ordered in, in 0.25, 0.5 and 1 cubic metre lots, with cartage on top, so the less you buy the more expensive it is per cub metre.
Allow 3/4m3 + 4 x 40kg bags cement + 4 x 40kg bags of lime per 1000 bricks laid with stretcher bond.
Specify bricklayer's 'fatty' sand because other sands tend to crumble and fall off when trowelled onto bricks.
Back to Contents

Step 5: Preparing the site

5.gif not found
Procedure:
Back to Contents

Step 6: Foundations

6.gif not found
Procedure:
Back to Contents

Step 7: Mortar

7.gif not found
Back to Contents

Step 8: Laying bricks

8.gif not found
Procedure:
Back to Contents

Step 9: Finishing

12.gif not found
Joints must be finished off before the mortar dries. There are many ways to do this (Fig 11).
Back to Contents

Step 10: Cleaning up

Never leave brickwork uncleaned for longer than 2 days after it has been laid.
Back to Contents

Step 11: Tools

13.gif not found
Tools are expensive, and sometimes an inventive person can use alternative methods, but usually by spending more time. Which is more precious to you: time or money ?
1. Stringline
2. Spirit level, long
3. Brickie's pins are flat with the blunt end flattened horizontally for easy hitting.
4. Steel meazuring tape
5. Club/mash/lump hammer (A claw hammer is too light and just bounces off the bolster.)
6. Brickie's trowel 280-300mm blade
7. Brickie's bolster
8. Bucket, large
9. Concreter's wheelbarrow, with a high front so mortar/concrete will not spill when moving. Many brickies mix mortar in this wheelbarrow but I favor the mixing board which is faster and gives a better mix.
10. Shovel, square-ended (not the spade in the diagram, which is pointed)
11. Gloves: strong, long and preferably waterproof since cement is damaging to the hands.
12. Bricklayer's steel scraper or a joint rule (to rake joints, if required)
13. Builder's square
14. Gauge rod
15. Joint rule
16. Hawk (mortar board), about 450mm square on which to place small amounts of mortar for direct application to the bricks. This square board has a thick (25-50mm diameter) rod screwed vertically to its center. Your hand then curls around this to hold it, and you dump mortar on the other side. Your trowel then cuts slabs of mortar off.
17. Mixing board for mixing mortar; 1m x 1m approx; must not leak.
15.gif not found
18. Carpenter's claw hammer (formwork hammer) [not shown]
19. Nails

Builder's square: essential for checking that corners are square (right angle, 90o). Make it from 75x25mm timber with the shortest side being over 600mm, the long side being over 1m and the diagonal over 1m. The triangle which you will make is exactly 600 x 800 x 1000mm. These meazurements must be exact because their ratio of 3:4:5, from Pythagoras Theorem, guarantees a right angle. Anything else is wrong. 'Near enough' is NOT 'good enough'. It must be exact. I prefer to mark the lengths on the outside, hold it together with approximate placing with small nails. Then get it exact; drill nail holes and nail with long strong nails.
17.gif not found

Nail them with a half-joint at the right-angle corner and the diagonal nailed on top. To make one that lasts, you can cut notches to allow the diagonal to fit snugly and flush with the side pieces.

Gauge rod: This ensures that the height of each brick course is accurate. Make it from 50 x 25mm timber at least equal to the full height of the brickwork. Mark lines square across the face every 86mm – the thickness of one brick + 10mm mortar joint.
In a garden wall this is not so critical, but if your wall has to be an exact height, such as 2.4m, you do not want to finish with a course height equal to half a brick. Adjust the mortar thickness to accommodate this problem. Make a gauge rod that will help you do this.
14.gif not found


Joint rule: Used to give a smooth concave indentation to your mortar joints. Take a 13mm pipe or mild steel rod (or use 10mm rod left over from the trench mesh for your foundations but I think 10mm gives too deep a concavity); and bend it into shape.
 
 
Back to Contents

Step 12: Checklist

Along with tools this is a minimum list. Your particular job might need extras, such as some stone work, or coloring for the mortar.
 
SupplierPhoneDate
ordered
Date
rec'd
MaterialsQtyPrice/
unit
Total price
  Bricks (material, style, color)
  Concrete for foundations
  Pre-mixed mortar or: *
  Bricklayer's 'fatty' sand #
  Cement
 Lime **
  Liquid plasticiser @
  Scrap timber for hurdles
 
  Tools to be purchased
  Total cost
  Money allocated

 * Dry mortar can be bought to avoid the tedium of mixing. Such bagged mortar is easier to move around and keep out of any rain. There is less wastage, and less time spend mixing. Any left over can be kept for another job. But it is more expensive than buying the 3 materials separately.
# Bricklayer's fatty sand, because other sands tend to crumble and fall off when trowelled onto bricks.
** This lime is slaked lime or calcium hydroxide, Ca(OH)2. Always check, because this term, 'lime', is also used for calcium oxide, CaO, which is caustic, and if water is suddenly added, generates dangerous heat which can explode boiling water over you.
@ or detergent; makes the mortar flow more easily so that it sticks to the brick while being buttered, and slides along the top of the course on which this brick will sit.
Back to Contents

Step 13: Tips

Tips: