Free Standing PierIf you are building a letter box,/mail box or a pier this is how you go about it.The principles are the same no matter what you are building. Method:
|
Profile/straight edge held steady by battens
|
| Profile held rigid The profiles are held in place with timber battens that are weighted with bricks to keep them stable. |
|
| Brick gauge See the marks on the profile, giving the height of the courses, that is, combined brick on mortar. Mortar is added to the brick, spread out, tipped mortar down to put on lower brick course, then tapped with the handle of the trowel till it exactly matches the mark on the profile. Mark the brick gauge on the profile, with usually 86mm per course, give or take. |
![]()
|
Piers and Fence | |
| Prepare the trench. Make the sides straight. Remove loose material from the bottom. |
|
| Set the concrete level. Drive in pins to set the level of the concrete. The two pins indicate a 1 course step in the concrete. Pour up to the pins. |
|
| Starter bars Put in starter bars to go inside the piers that carry the gate. The gate piers will be filled with concrete to add strength. |
|
|
Step formed in concrete. |
|
| Profiles & stringline Set up the profiles and run a string line between them, so that the piers will line up. The concrete strip between the gate piers stop the piers from going out of alignment over time. |
|
| Wall ties Starter bars and conduit being bricked in, the conduit is for the power cable, lights will be added to the tops of the piers. Wall ties are built into the pier so it gets tied in with the concrete fill. The Piers were filled with fine concrete after they had gone off for a few days. Because the front and rear piers are offset from each other the end bricks of the wall had to be cut on a slight angle. |
|
| Pointing When pointing, angle the perps the same way. Otherwise the wall looks messy. |
|
| Pointing - closeup To point, put the same side of the trowel into the joint on every perpend. |
|