Corrugated steel

This article, apart from my insertion of advantages and disadvantages, comes from an advertisement. Having roofing experience, I agree with the information selected here. No benefit accrues to PT from this chapter.

[Fasteners or screws have their diameter given as a gauge, denoted by #, as in #12 and #10.]

Advantages

Disadvantages

Roofing & Walling

Corrugated steel gives you the versatility of a traditional corrugated roof or wall cladding profile with the strength and light weight of a modern steel building product.

Corrugated steel is roll-formed and is available in a wide range of colors. Corrugated steel is a cheaper cladding for many building applications.

Installation

The sheets of Corrugated steel overlap each other and are fixed progressively along the building in the opposite direction to the prevailing weather. This gives complete weather protection and a fast and efficient method of installing the roof.
Each sheet includes an “under” rib and “over” rib to form an anti-capillary drain which prevents water entry at side laps.

steelclad_762_diagram7.gif

Preparation

Packs of corrugated steel can be lifted onto the roof frame so that all sheets are the right way up and with the over edge facing the end of the roof where laying will commence.
Prevent roof damage by walking on at least two ribs to distribute the weight over the foot and walk across the roof over the supports (battens).

When the roof pitch is less than 250 or where there are extreme weather conditions, turn the sheet ends up about 800 at the high end and down about 150 at the gutter or low end. A shifting spanner can be used to do this.

End lapping

When two or more sheets are required for full length cover, start laying at the gutter and work up to the ridge and then start the next run at the gutter again.
The minimum end laps required are:
End laps:

Recommended fasteners

Steel Framing (up to 5mm):
Timber Framing:

Side lap fasterners

These are added to give weatherproofing at the midspans of the sheets for support spacings over 900mm for roofs and 1200mm for walls. Use #8 x 12mm Hex Head Type 5 Self Drilling Screw with Neo. Washer or blind rivets.

Method of fixing

Roofs – Screw through the crests only, using 3 fasteners/sheet or 5 Fasteners/sheet depending on the location. At the end sheets 5 Fasteners/sheet must be used. (For steep gable roofs, because of the lifting action of gale-force winds, I would use 5 fasteners throughout.)

Walls – Screw through crests or valleys. 3 Fasteners/sheet or 5 Fasteners/sheet can be used depending on location. At the ends of sheets 5 Fasteners/sheet must be used. If valley fastening is used, side lap fasteners must be added beside each main fastener.

Precautions

Always use a spreader bar and fabric slings to prevent damage when unloading bundles of sheeting with a crane. When manually handling sheets use clean dry gloves and do not drag sheets over each other or use disk grinders within reach of sprayed metal dust. Storage of sheets should be above ground and under cover.

Crest fasteners must not be overtightened but driven in until slight deformation of the rib is observed and the neoprene waster is fully sealed.

Do not locate fasteners less than 25mm from the end of sheets. Do not use punches to form holes for fasteners. Holes must be drilled or self drilling fasteners used.

Coverage

Corrugated steel has an effective coverage of 762mm when laps of 1.5 ribs are used.

Roof pitch

Corrugated steel is designed so that sheets overlap by a minimum of 1.5 ribs, which prevents the entry of water. The minimum recommended roof pitch is 50.

steelclad_762_diagram8.gif

Non-cyclonic

steelclad_762_diagram9.gif