Proportioning and mixing concrete
A concrete mix is designed to produce concrete
that can be easily placed at the lowest cost.
The concrete must be workable and cohesive when
plastic, then set and harden to give strong and
durable concrete.
The mix design must consider the environment that
the concrete will be in, such as exposure to sea water, or its traffic
(trucks, cars, forklifts, foot traffic) or extremes of hot
and cold.
Proportioning
Concrete is a mixture of:
- Cement
- Water
- Aggregates - both coarse and fine
- Admixtures.
The proportions of each material in the mixture affects the properties of the final hardened
concrete. These proportions are best measured by weight. Measurement by volume is not
as accurate, but is suitable for minor projects.
Cement content
As the cement content
increases, so does strength and durability.
Therefore to increase the strength, increase
the cement content of a mix. Obviously excess cement will lack enough aggregates to make a concrete and so become powdery. For example, the poor practice of sprinkling cement on the surface to absorb excess water, makes the surface weak and powdery.
Water/cement ratio
Adding more water gives a weaker concrete. As the Water-to-Cement ratio increases, the strength and
durability of hardened concrete decreases.
To increase the strength and durability of
concrete, decrease the Water-Cement ratio.
Always use as little water as possible, just
enough to make the mix workable.
(See 2 Concrete Properties)
Aggregates
Too much fine aggregate gives a sticky mix.
Too much coarse aggregate gives a harsh or boney mix.
(In 1963 I worked on the construction of a wheat silo at Chinchilla, Queensland. During construction many sections of the walls fell away, some of them huge, owing to lack of a balanced range of aggregate sizes - very little sand and small aggregate, coupled with large rounded aggregate instead of crushed rock. To my surprize it is still standing, but its many visible patches remain witness to a shonky company.)
Mixing
Concrete must be mixed so the cement, water,
aggregates and admixtures blend into an even mix.
Concrete is normally mixed by machine (concrete mixer).
Machine mixing can be done on-site or by a pre-mix
concrete company. Pre-mixed concrete is batched
(proportioned) at the plant to the job requirements.
Truck mixing
The materials are normally added to the
trucks at batching plants and mixed for required time and
speed at the plant. The truck's drum continues to rotate to
agitate the concrete as it journeys to the site.
Site Mixing
When site mixing:
- Begin by loading a meazured amount of coarse
aggregate into the mixer drum.
- Add the sand before the cement, in measured amounts.
- Meazure with a bucket.
Never use a shovel as a meazure since volumes can then vary widely.
- Mix materials together until there is no visible sand in the mix.
- Add enough water to get a workable mix.
Caution:
- Be careful not to overload the mixer. Too much
concrete in the mixer means each batch takes longer
to be properly mixed, which causes costly delays
in the long run or it will not mix at all.
- Always check how much the mixer holds so you know
how much concrete can be produced at once.
- Avoid delays between batches to get maximum output.
- Mix the materials together until they are even.
- Small quantities of concrete may be mixed by hand with
a shovel. Mixing should be done on a clean board, or plate. Some mix it in a wheelbarrow but do they mix it thoroughly ?
- Then form a hollow in the mix and add water. Use only enough water to get
an even, workable mix. (Add less than you think you need; add a volume of water [litres] less than 1/2 the weight of cement [kg].) Finish mixing.