Planning and Site Preparation
The most important step in placing concrete is planning.
Always plan every step before any concrete is delivered.
Proper planning avoids delays, wastage, segregation of the components of concrete, and
problems which develop from these.
To eliminate problems of delay, segregation and wastage, see 7 Transporting and Placing Concrete.)
Safety
Safety includes:
- Every person on the site is responsible for the safety of all other workers on site. If you see any action putting another at risk, it is your responsibility to report it to the foreman.
- Workers on the site should always wear protective
clothing, strong boots and, if required, helmets or eye protection.
- Always avoid direct contact with cement and never kneel in or
touch the concrete mix directly.
- Wear gloves and use barrier creams.
- Ensure that anyone using heavy equipment, such as screeds or
vibrators, has been properly trained.
Planning
- Meazurement:
Meazure and stake out the area to
be concreted and consider how thick the slab must be.
The thickness will depend on the weight the concrete
must carry (ie driveway carries the weight of a car
and needs to be thicker than a garden path).
- Finishing level:
Once the thickness of concrete has been established, work out
where the concrete will finish. Concrete cannot finish too high against steps or the external
house wall and should not cover any part of weepholes in the wall. The finishing level
shows how much digging or excavation must be done. Pavements must grade away from
buildings and boundaries. In Australia the national building code (handbook) should be consulted.
- Steps:
Steps must have even risers. The angle of the rising steps might have to conform to the building code.
- Excavation:
The ground should be excavated as deep
as is required by the finishing levels. It may need to be deeper, because grass, roots and humus must be dug out until there is firm sub-soil for the footing. Always
dig the hole wider than needed to allow for the formwork.
Try to keep the edges and corners square.
- Subgrade:
The soil which a concrete pavement or
floor rests on is called the subgrade. If the soil is
soft or varies in softness, a layer of crushed rock
should be added. If there are only a few poor areas
these can be dug out, refilled and compacted. It is
important that the soil evenly supports the concrete.
Many later problems can be avoided by properly
preparing the subgrade.
- Formwork:
Formwork gives concrete its shape.
Formwork must be properly braced so it is strong.
It should not flex or move. Rodding, compacting the concrete to remove the air, puts great strain on formwork.
(See Formwork.)
- Services:
Plumbing, heating or electrical
services often run through a slab. These must be
in place before any concrete is poured.
- Underlay & services:
The underlay, or
vapour barrier, is a heavy plastic covering the
ground to minimise water vapour rising through the
hardened concrete:
- Always overlap the sheets a
minimum of 200 mm and do not tape them.
- Tape
the edges of underlay only around drainage pipes
or services which pass vertically through the
concrete slab.
- Termite protection may be required around service
penetrations and around the perimeter of the slab.
- Reinforcement location:
Reinforcement can be used to increase the strength of
concrete and/or to help control cracking. Because concrete is weak under tension but strong under compression, reo is placed in the layer which is stretched:
- When a slab is on the ground, increased moisture in the clay will cause it to expand, pushing the concrete slab up. Therefore the top of the slab is stretched. Thus the reo must go in the top third of the slab.
- For a suspended slab, any weight on the floor will bow it downwards, stretching the underside. Thus the reo must go in the bottom third of the slab.
- For trenches and footings, the weight of the house presses downward as the clay shrinks, causing the underside to stretch. Thus the bottom third needs reo.
But when rain causes the clay to expand, the topside of the footings stretch. Thus the top third needs reo.
The pictures of footings in Concreting Part 2, show both positions for the reo.
The reinforcement must be covered by a set amount of concrete which protects the steel
from rusting. This is called cover. Cover is measured to the nearest surface. The amount of cover depends on whether the concrete is inside a building or
outside in the weather.
Reinforcement should be securely held during the pouring of concrete. When reo ends and a new on begins, they must overlap a
set distance or from one piece of reinforcing bar, or wire fabric, to another and at the
corners of a trench. These distances are specified by the country's building code.
(See Reinforcing)
- Access:
Clear access must be provided to transport the concrete.
If concrete is to be delivered by trucks make sure they have unrestricted access to, and exit from, the site in all weather conditions.
- Placement:
Ensure all planning and site preparation takes into account how concrete
will be placed:
- allowing room for trucks, including turning circles
- ramps for wheelbarrows
- space for a concrete pump etc
- allow clearance under electric and phone cables, because concrete trucks are high
- ensure the heavy concrete trucks (up to 14 tonnes) will not damage underground cables or churn up driveways.
- To protect driveways put down broad thick timbers from a metre on the road across the gutter and sidewalk. These will spread the load over a greater area. Often there are major pipes under the sidewalk (electric, reticulated water, stormwater) and if you damage these, the local authority will demand payment for repairs.
- Joints:
The position, type and number of joints should be planned well before the
concrete is placed.
(See Joints.)
- Wastage:
Good planning and site preparation reduces wastage. Reducing wastage can
cut costs, since up to 15% of concrete can be lost this way.