Transporting and pouring

Avoid

When transporting and placing concrete, avoid:

Transportation

The method used to transport concrete depends on which one minimizes cost and is easiest for the job size.

Some ways to transport concrete include: Transport concrete as little as possible to reduce problems of segregation and wastage.

The wheelbarrow

On small jobs a wheelbarrow is the easiest way to transport concrete:

Placing

When placing concrete be careful not to damage or move the formwork and reinforcement.
Place concrete as near to its final position as possible.
Start placing from the corners of the formwork or, in the case of a sloping site, from the lowest level.

Safety

When using cement or fresh concrete, avoid skin contact.
Avoid breathing cement dust.
Wear protective clothing.

Delay

Delay can cause the concrete to dry-out and stiffen.
Delay is more of a problem on a hot, and/or windy, day when the concrete will dry-out and stiffen more quickly.
To avoid delay plan ahead. Check that all labour, tools and containers are ready and that all preparations for placing have been done before the concrete is delivered.

Never just add water to the concrete to make it more workable, always use a mix of cement paste, that is, water with cement. Beware truckies who keep adding water for their own convenience, weakening the concrete and increasing shrinkage and cracks.

Segregation

Segregation is when the coarse and fine aggregate, and cement paste, become separated. Segregation may happen when the concrete is mixed, transported, placed or compacted.
Segregation makes the concrete:
To avoid segregation: (See Compacting.)

Wastage

Wastage can be costly, especially on small jobs, where wastage as a percentage or requirements or as a proportion of total cost, can be high. To minimise wastage; mix, load, transport and place carefully.