Compacting Concrete

Compaction is the liquefying of concrete by shaking or vibrating, thus allowing the trapped air to escape and the concrete to settle, filling all the air-pockets between the forms.

When to compact

Compaction must be done as concrete is placed, while it is still plastic. Never let concrete dry-out and stiffen because it will be too hard to compact.

Why compact ?

Properly compacted concrete is more dense, strong and durable. Where the forms are removed, the concrete surface looks smooth instead of spoiled by air-pockets.

External vibration

External vibration is called screeding. Wheile leveling, screeding compacts thin concrete slabs. Screeding compacts the top layers of thicker slabs.
There are two types of screeding: Concrete is screeded twice.
The first screed levels the concrete roughly and compacts it.
The second screed levels more accurately, while compacting further.

Internal vibration

Internal vibration is done with a mechanical vibrator or poker vibrator. The poker is put into concrete and vibrates it from the inside.

Method

Method:

How long to compact

For concrete of average workability (ie slump of 80 mm) with a poker size between 25–75 mm, concrete should usually be vibrated for between 5 and 15 seconds.
It is worse to under-vibrate than to over-vibrate concrete.