Dry stonewalling Part 1
This chapter was kindly given by John Vivian, whose book Building Stone Walls expands beyond this chapter by discussing how to quarry rock and build stairs, stiles, gates, and retaining walls. Why not buy it ?
Contents
Intro
Definition: Drystone-walling builds structures from stones without any mortar to bind them.
A drystone wall is actually two separate walls with a middle filled with smaller rocks and pebbles. The two separate walls are interlocked at regular intervals by tie-stones which stretch across both walls and the middle. The 2 walls lean inwards towards the middle, and are capped by a row of single stones along the top, to shed the rain.
Traditional poem
Wiltshire, UK
I'm a drystone waller.
All day I drystone-wall.
Of all appalling callings,
Drystone-walling's wors' of all.
Drystone structures are stable because:
- large angular stones, snugly fitted
- great width gives stability
- the middle is filled with stones, not dirt which would be washed out by rain and encourage weeds
- good rock foundation
- the vertical crack between 2 adjacent stones, is covered by a third stone, thus interlocking the two adjacent stones by its weight.
- long stones interlocking the outer walls
- inward leaning prevents upper rocks being knocked loose by stock
- capping prevents weed growth (weed roots can displace stones)
- minor maintenance by farmers.
Drystone work includes thousands of kilometres of stock fencing, retaining walls impressively in ancient roadworks, buildings, bridges, ancient forts and even artwork.
As the photo of a wall with steps shows (see previous chapter Stonewalls), mortar spoils the beauty of a stone wall. Instead of your next brick or block barbecue wall, why not try drystone walling ? Whenever you wish to enlarge, re-shape or re-fashion it, a drystone wall is easily dismantled and rebuilt.
Caution
Think small.
They measure stone in tons.
Pushing a wheelbarrow with 2 stones in it, up a even very low incline, is very hard on your back.
Lifting a heavy rock is dangerous; dragging it up a slope is tedious. Spending a day lifting heavy rocks onto a wall is back-wearing. A tired back is a disaster waiting to happen. You do not understand pain until you have a bad back; a collapsed disk can ruin your life. Keep the weight of rocks within easy lifting. Do not overestimate your strength or endurance.
Care is the word:
- If you drop a rock on your toe, your toe splatters like spaghetti. Wear steel-capped boots.
- Stone scrapes the skin off your hands, and the dust penetrates all scratches, even your pores. Always wear heavy-duty work gloves.
- Stone dust causes emphysema, so if dust is in the air, wear a dust-mask.
- If you or your mate is chipping or breaking stone, a flying chip can blind you for life. Wear protective glasses.
- If you have any physical problems, try to work with a partner in case you need help.
- if you're feeling tired, take a break – fatigue increases risk of serious injury.
Note: Be aware of building codes and property laws. If you live in an area that's prone to earthquakes, codes may prohibit this type of wall. If you're building to mark your property line, avoid misunderstandings by consulting your neighbors beforehand.
HowTo
A stone wall is narrower at the top than at the base; two separate but interlocking walls, tied at regular intervals by longer through or tie stones, and a middle filled with a mass of smaller rocks and pebbles.
To build a wall:
- Make two timber A-frames whose outer edges will match the outer faces of the wall. Erect one at each end of the intended wall, by standing each frame on the ground then tying to 2 long wooden pegs hammered into the ground.
- Stretch two strings between the A-frames to show your base lines of the wall. (Thin braided nylon string is best but any strong string will do.)
- For a long wall, drive pegs into the ground at intervals along the strings. Or run some flour or chalk along the stringline, or mark the ground with a pick or spade.
- Remove the A-frames and stringlines temporarily while you dig. Dig a trench between your flour-lines. The trench is shallow but the layer of humus should be removed because as humus breaks down, the volume of soil shrinks, causing the wall to sag unevenly.
- At the ends you will build square quoins, so place large flat stones in their part of the trench as foundation and fill their gaps with aggregate.
- Line your trench with aggregate (crushed rock), sufficient to wriggle your base stones into and be held firm. If your soil is hard clay which cracks in the dry season, you cannot use sand because this will disappear down those cracks, causing the wall to sag unevenly.
- At both ends build quoins or cheekends, which have to be the same width all the way to the top; solid, square and vertical, locking into the next part of the wall with several long stones jutting out. Use your A-frame to decide which stones should jut out. Use a plumb bob or level to check for plumb (vertical). In each layer, the gap between any 2 stones is covered by the stone in the layer above. This ties it all together. Since quoins are knocked by passing traffic, you might place a guard post on each side of it.
- Place your A-frames inside the quoins and replace the stringlines. Then begin the wall, placing the biggest stones at the bottom, along the outer edge of the shallow trench. Wriggle your base stones into the aggregate till held firm, with a gentle slope downwards from center to outside wall, to shed rain.
- Begin the second course, placing a stone over each gap or joint in the stones below in the first course. If a stone wobbles then pin it up with a stone fragment securely placed. Do not use sand or soil, because these attract weeds which push stones out of place, and are themselves washed out by rain, causing the wall to cave in on itself. Maintain the slope established in the first course.
- The tie stones, stones going right across the wall to tie the two sides together, are placed about every metre.
- Lay large flat stones on the top.
- For coping, cap or capping, stand upright cope stones along it, using bigger heavier ones at regular intervals, with smaller, lighter ones wedged in between. Since children might knock these off, some wallers mortar them in place, but that defeats the purpose of dry stonewalling.
- Pebbles are hammered down between the cap stones, locking them all in place.
The waller's only tool is a sharp-edged hammer (a geologist's pick/hammer), used to dress stone if unavoidable. Sometimes the stone is too hard to chip, but in a field of rocks, pick another.
The UK claims 125,000 miles of dry stonewalls. A few are ancient, dating back to 3,500 BC. Most are field walls and went up in the early- to mid-1800s, in the wake of the enclosure acts. For a century they were well maintained, but these days, farms lacks the resources. Dust blows by and settles in with seeds; seeds sprout and roots push the stones apart.
Labour and materials for a 1.5m-high dry stone wall can cost £270 a metre (in 2009), so rarely do new walls go up except in landscaped gardens and the wealthier apartment estates. Stonewallers survive on repairs to old walls.
An experienced waller can do three metres in a day, which entails lifting about three tonnes of stone (six if he's rebuilding). Wages are obviously not the attraction, but leaving the district with a fine stonewall that will last centuries, justifiably adds to one's self-respect. [Jon Henley, The Guardian, 08Aug2009]
The instructions below are for perfect retaining walls, but in many countries
perfection is too expensive. Therefore take cost-saving 'shortcuts' while aiming for stability and long-life. However, do not fill the gaps with sand or soil, because these can be washed out by the rain, causing the wall to collapse. The gaps can be filled only by hard fragments of rock, either chinks or aggregate (coarsely crushed rock). All rock must be weather-resistant. Stone like soft sandstone is not suitable.
Overview
Traditionally, stonewalling arose from the need:
- to keep stock in at night or out of crops
- to defend against predators and raiders.
Stone was chosen because:
- stone was plentiful and free
- Stone walls did not rot like timber palisades
- pasture benefited from the removal of surface stones.
Here is a summary of the method of dry stonewalling, which has some points not mentioned in the main discussion.
A retaining wall:
- Natural selection:
A good-looking, stable wall depends on stone selection. Choose square, chunky stones as these jigsaw together better than round or oval shapes. The best walls have minimum gaps. Use different sized stones for different parts of the wall (see Diagram 1). Select:
- base stones about 300-350mm long
- wall stones about 250-300mm long
- wall stones about 250-300mm long
- capstones or head stones about 200mm long
Separate stone into course-size groups for
faster selection; placing the biggest nearest the trench, and the smallest farthest away. Leave plenty of room to work; you cannot risk tripping when your hands are full of rock.
- Step 1 Prepare the foundation:
Establish the line of the wall with pegs and stringline, then cut back the slope. At the base dig a 200mm deep, 600mm wide trench. Separately pile topsoil and subsoil nearby to make it easier to backfill later. Fill the trench with a 100mm bed of 20mm aggregate.
Tip: The line of a straight wall can be set with pegs and a stringline.
- Step 2 Lay the first course:
Lay large base stones along the outer edge of the trench. Roll in any rocks that are going to be too big to lift up onto the upper courses.
- Step 3 Add fabric and backfill:
Tuck geotextile landscape fabric in behind the first course, fold it over the rocks, shovel in backfill and tamp soil by pounding with a post. Repeat this entire process after each course.
Tip: If the site is wet, lay a length of agricultural pipe behind the base stone so that any water will be diverted to an exit point.
- Step 4 Build with wall stone:
Lay the fabric back against the slope and set the wall stone courses. Each course should be wider than the previous one. Three courses are shown here.
Tip: It is best to complete an entire course before moving onto the next.
- Step 5 Wedge the gaps:
Drive chinking stones or wedge stones into the face of the wall to fill any gaps or secure loose rocks. When doing this, wear safety glasses to protect eyes from flying shards of stone.
Tip: For a more balanced effect, use small pieces or wedges to fill holes.
- Before deciding to cap the wall, decide whether the wall is the best you can do. If not, pull it down and start again. Your self-respect demands professionalism.
- Step 6 Level the capstone:
Lay capstones, checking with a level as you go. Capstones should bring the wall to a height that is roughly level with the embankment. Mortar small capstones in place for permanency. Tuck the
fabric in behind the capstones, backfill and add top soil.
Tip: Lay the capstones to a stringline to ensure they are level.
Equipment
The Necessities:
- stone (see Step 1 for options)
- aggregate
- work boots, steel-capped
- work gloves
- measuring tape
- level
- shovel
- sledgehammer
- brick hammer
- crowbar
- safety glasses, earmuffs
- wooden stakes
- string
- 1 by 2-inch (2.5 by 5-centimeter) board, cut to the height of your wall
- saw
Optional:
- wheelbarrow
- 2 or 3 x 10-gallon buckets
- commercial hand tamper
- 2 by 12-inch (5 by 30.5-centimeter) board for tamping
- drainage perimeter pipe
- landscape fabric
Time
The amount of time depends on the size of your wall. For a 60 cubic foot wall (18.3 cubic meters, the limit recommended by this chapter) allow at least three full days of work.
Tips
Tips:
- Need wall ideas? Check out landscape design magazines, or stonework brochures from the supplier. Just stay clear of overly complex designs that need professional skills to assemble.
- For a little extra, you can sometimes buy stone with lichen or moss already growing on it, for that pre-aged look.
- If you want to use stone gathered from your own property, be aware that you might need more than what you have available (and that, as a rule of thumb, you'll always need more than you think you will). Consider taking a sample to a supplier to make sure it can be matched, if necessary.
- Have the stone and aggregate placed as close to the working area as possible, without, of course, blocking the wall's placement.
- If you're building a long wall, you may want to have the aggregate dumped in multiple piles along the planned course for easier access.
- If your aggregate pile isn't easily accessible, a good way to transport it to the wall is with a wheelbarrow or large buckets (10-gallon drywall buckets work well). Just fill them at the pile, carry them to the wall, and pour them in.
- When laying out the base stones:
- bend your knees
- straighten your back
- place your hands on opposite corners, preferably with corners you can grip
- drop the stone from your hand from about 6"/15cm above the aggregate to seat them and compact the aggregate for added stability. Use this technique when setting the rest of the stone, so the wall settles as you go.
- To create chink stone, place a larger stone on the ground and break it into pieces with your sledgehammer. Always use protective glasses when doing this, and try to use stone that isn't useful in its current form.
- If the top of a set stone does not cant enough toward the wall's center, don't worry. You can lay chink stone on the top to make the next stacked stone cant correctly.
- You can shape a stone by chipping off its thinner edges. Hit it hard with your brick hammer's sharp end until you have a score line around the area you want to break off. If the piece doesn't break, keeping hitting along the score. Don't expect a perfect break every time.
- As you build your courses, alternate the placement of the cornerstones. For example, if one cornerstone ties the side, on the next course, set in two or three cornerstones that run perpendicular to it.
- Try to set tie stones in your courses about every 4 feet (1 meter).
- If you want to adjust a stone that's already set, push the flat edge of your crowbar underneath the stone and use the stone beneath it for leverage. You'll be able to move it much more easily than if you use your hands.
- Cut a 1 by 2-inch (2.5 by 5-centimeter) board to the height you want your wall, so you have an easy reference check as you build.
- To check the wall's cant, hold the reference board with one end resting on the ground and touching the bottom edge of the base stone. Hold your level against one side of the board to make sure it's perpendicular to the ground, then use your measuring tape to check the distance from the board to the wall's face.
- If you want a level top to your wall, plant stakes firmly at each end of the wall before you reach the last course, then tie a string between the stakes as high as the wall's projected height. Hold your level up to the string, adjusting it until it's level. Once it is, build the remaining course and capstones up to the string.
- To calculate the amount of aggregate you'll need as backfill, multiply the height of the wall with its length, then multiply this with the rough distance between the top of the wall and the point where the embankment begins to slope. Divide this figure by two.
- Even with only one exterior side, a retaining wall still needs tie stones. Lay them regularly so one end enters the backfill. This will anchor and strengthen the wall.Even with only one exterior side, a retaining wall still needs tie stones. Lay them regularly so one end enters the backfill. This will anchor and strengthen the wall.
- Tamp down the backfill aggregate as you build so the wall is regularly settled.
- If you're building at the bottom of a long slope or hill, the runoff (the water that moves through the ground) could be significant enough to require a drainage perimeter pipe, available at hardware and landscape supply stores. Lay the pipe against the back of the base stones, on top of the drainage layer of aggregate, then backfill aggregate over it as you build. Follow the package directions regarding fitting and sloping the pipe.
Step 1 Design the wall
The more effort you put into planning, the less likely you'll be to run into unexpected problems when you build. As you start plotting out your wall, keep three things in mind:
- Scope: As mentioned previously, you don't want to get in over your head. Even if you have a grand plan for your wall, start small. It's best to build no more than 60 cubic feet (18.3 cubic meters) at a time. For example, a wall that's 2.5 feet high, 1.5 feet wide, and 15 feet long (.76 by .45 by 4.5 meters) is about 56 cubic feet. Staying in this range should give you a good feel for the physical and technical demands of stonework, without too much strain. And remember, you can always add more later if you want.
- Fit: A good design complements its surroundings, so try to picture the finished wall within its planned setting. Will a soft curve work best, or a more regimented straight line? A low wall, or one that's slightly higher? Consider your present landscaping style: A more meandering garden might fit well with rougher-looking stone, while for a carefully manicured yard, you'll probably want a cleaner, more formal design. Also, don't forget that stone can come in a variety of colors--consider what shade will balance with the house and landscape.
- Stone: The best way to decide on stone is to go to your local supplier (check under "landscape supply" or "stone" in the phone book), describe your project and the "look" you want, and see what they recommend (and what they have in stock). The most commonly used wall stone is faceted, that is, with easy-to-stack, squared-off faces--key for a solid construction. There are many varieties of faceted stone, with differences in color, shape, texture, and price.
Other wall choices include river rock, rounded stones that you should probably avoid, since you'll need a very wide base to stack them safely, and flat stone, rock such as shale or slate that comes in thin slabs. Flat stone can make fine drystack walls, but it usually costs significantly more, since its smooth surfaces are better suited for more polished work.
Whatever your decision, remember that your wall will only be as good as its materials, so go with quality. Cheaper, more roughly shaped stone may seem like a good buy, but it can add a lot of difficulty to the construction while being less pretty.
Step 2 Calculate your materials
Once you've chosen your stone, it's time to put on your math cap and figure out just how much stone and filler you'll need. Here's how:
- Decide on the wall's dimensions. (If you've already figured the rough size, it's time to get specific.) Measure out the length with a measuring tape. For the height, stay under 2.5 feet (.76 meters)--anything higher could have stability problems. The base should be roughly three-quarters of the height, unless it's a low wall (under 1.5 feet, or .45 meters), in which case it should match the height.
- To find the amount of stone you'll need, multiply height times width times length to get the total cubic area of the wall. Next, divide this figure by 15 to calculate the stone in tons (15 cubic feet of stone is roughly 1 ton, the unit in which stone is sold), or by 4.57 to calculate it in metric tonnes.
- You'll also want filler, or aggregate--bits of washed stone to put between the exterior sides of the wall and below it, for stability and drainage. Aggregate is sold by the cubic yard, which is 27 cubic feet (about 9 cubic meters). The amount you'll need can depend on the type of stone you use, so get the stone supplier's recommendation before you buy (these places will commonly sell aggregate, too). A safe bet is about half of the total cubic feet. Dividing the total cubic feet by 54 (27 times 2) will give you that figure in cubic yards.
- If you're wondering why you'd need the full amount of cubic feet in stone, in addition to half in filler, the reasons are stability, selection, and security. First, you'll need a little extra aggregate for the base layer below the wall. Some extra stone will give you more sizes and shapes to choose from, which is crucial to a well-built wall. And finally, remember it's better to have too much than too little.
Step 3 Gather and sort your materials
When you're ready to order your materials, be sure to tell the supplier what size aggregate you want (3/4 of an inch, or 1.9 centimeters, is best--big enough to not slip through the joints, but small enough to shovel easily). For the stone, you'll want a variety of sizes. Expect a rough mix of these five shapes:
- Cornerstones: Large stones with 90-degree angles that you can use for wall corners
- Capstones: Large, flat stones that "cap" the top course of the wall
- Tie stones: Long stones that lay across the full width of the wall, "tying" the two sides together for added security
- Base stones: Large, stable stones used for the first course
- And finally, mixed grade, which includes everything in between.
Unless you want to pick up the stone yourself, the supplier will deliver it (usually for an added charge). Stone typically comes on pallets so they can be placed wherever you want. The aggregate will usually be delivered in a dump truck and deposited in a pile.
Once the stone is delivered, it's up to you to unload it from the pallets. As you do, try to sort it by the shapes listed previously. This way, you won't waste time searching for the right size when you start building.
Step 4 Dig and line the base
The stability of your wall will largely depend on its base, so here are the steps to setting it up correctly:
- Mark off the base's dimensions (width and length) by tapping wooden stakes into the ground at each of the wall's corners, then tie string lines between the stakes and close to the ground. Note: If your wall is curved, you can mark the edge by tapping in evenly spaced stakes along the curve, then connecting them with string. Or try laying out a garden hose along the edge--this will give you a smooth curve every time.
- Within the dimensions, dig a 4-inch (10-centimeter) deep trench if the wall is shorter than 1.5 feet (.5 meters). If it's higher than that, dig the trench 8 inches (20.3 centimeters) deep. Remove any roots or rocks so you have a level trench bottom.
- For a shorter wall, line the trench with two inches (5 centimeters) of aggregate. For a taller one, line it with a 4-inch (10-centimeter) layer of aggregate.
- Tamp down the layer. You can do this using a commercial hand tamper, but laying a board over the layer and jumping on it a few times works just as well.
- With the recessed trench providing snug security for your first course, and the aggregate allowing for proper water drainage, you're ready to start building.
Step 5 Lay the base stones
As you start your stone-laying extravaganza, don't forget to stretch those muscles first, lift with your legs, not your back, and keep these guidelines in mind:
- Start at one end of the wall, laying the cornerstone in the trench first. If possible, try to find a cornerstone that "ties" the corner--that is, lays across the full width of the wall.
Lay down the base stones, one after the other, by butting them together in two parallel rows on either side of the wall. Leave space between the rows where aggregate filler will go. Try to lay a tie stone every yard or so for strength.
- When you pick the base stones, don't worry if they match in height. The most important criterion is that each stone has two fairly flat faces - one to sit on the aggregate drainage layer (usually the larger face), and one to point out from the wall (hopefully, the better-looking face). For the top face (onto which the next course will be laid), the one key requirement is that it doesn't slant away from the wall's center. If anything, it should slant toward the center, since you want your successive courses to "cant," or slope slightly inward. This allows the wall to stabilize itself.
- Stone walls look best when the joints (the spaces between the butted stones) are tight and complement each other, so try to pick base stones that will butt together in this way. If you can't find a good match, don't worry. You can always add "chink" stone, that is, small, broken pieces of larger stone used to fill in larger joint gaps, or to help correctly cant the stone.
- Once you've finished laying the base stone (with another nice cornerstone or two at the opposite end), shovel in the aggregate filler, enough so it crests the tops of the shorter stones.
- As you build, you'll notice that laying wall stone is a little like solving a giant puzzle. What you put in early on can have a big effect on what you set on top of it later, so don't rush the work.
Step 6 Build the courses
In masonry, a course is a continuous, level layer of stone, which, when stacked on top of other courses, forms a wall. However, since typical wall stone isn't uniform in size (like brick), a drystack course won't be one level layer of stones, but a mix of sizes and shapes fitted together into one roughly level layer of stones (onto which you build the next course). To get started, follow these guidelines:
Placement: With the exception of laying the base stones, build each course by starting on either end of the wall and regularly alternating between the two ends until the two sides meet in the center and the course is completed. This will help tie the wall together.
- Height: Each course's height depends mainly on the size of the stone you use for it. For example, to create a level course with the base stones, you need to stack on top of the shorter ones to square them up with the taller ones; thus, the taller stones determine the height of that course. (Courses typically range from 6 to 12 inches, or 15.3 to 30.5 centimeters.)
- Levelness: Remember: roughly level. With the course layer's crest, you mainly want to provide a stable shelf for the next course, and ultimately the capstones. If the layer wanders up and down a little, that's fine (although for the last course, you'll want a fairly level base for the capstones).
Joints: When you start a new course (or stack rock within a course) always cover the open joints of the butted stones below it. It's a good policy to have no more than three stones coming together vertically (usually in a T-shaped joint). Too many vertical joints (four stones or more, forming a cross) can weaken the wall's integrity.
- Canting: This is absolutely critical to the wall's strength. The rule of thumb is to cant each side toward the center 1.5 inches for every foot (3.8 centimeters for every 30.5 centimeters) on either side. Measure regularly as you build the wall up.

- Filler: Continue to add your aggregate filler as you lay your stone. By keeping the filler level crested with your building height, you provide constant stability and backing to the stones. Remember that the aggregate can help form the shelf onto which you stack your next course.
- Facing: Don't forget about looks. Keep your joints tight and complementary, using chink stone when needed, and try to orient the stone's best face forward, with its edges as flush as possible with the surrounding stone. Alternate shapes, sizes, and placement. Just remember to save enough of the special stone (such as cap, tie, or cornerstones) for their particular areas.
- Once you develop a rhythm for the work and a feel for the stone, you'll be surprised at how involving an activity this is. Mind and muscle combine, and piece by piece your vision becomes reality--a very satisfying process from start to finish.
Step 7 Build a retaining wall (optional)
With a few tweaks to the design, a dry stone wall can turn into a functional (and beautiful) retaining wall. Here's how it's done:
Dig a drainage area: Since the wall will have soil behind one side, it'll be in contact with a lot more moisture. This means you'll need to provide a drainage area behind and below the wall. To start, mark off the wall's base and dig a trench, with the width equaling three-quarters of the wall's height. The trench's back edge should run along the soil embankment. Next, if the embankment isn't naturally sloped, you'll need to dig out enough soil, starting at the back edge of the trench, to create an incline that's about 6 inches for every foot of height (15 centimeters for every 30.5 centimeters).
Build and fill: Line the trench with aggregate, tamp it, lay in your base stones and start building your courses. Since you'll only be building one face, backfill aggregate between the stone and the soil slope as you create the courses. Use the same construction techniques explained earlier, with the exception of canting. Here, you want a slightly steeper cant, about 2.5 inches for every foot (6.3 centimeters for every 30.5 centimeters), since the wall will be supporting more weight. Angle the stones toward the slope when you seat them in the wall.
- Cap the wall: You can either build right up to the embankment level, with the aggregate backfilled behind it and showing on the surface, or, for a more natural finish, you can cover the aggregate with soil to grow plants right up to the wall's edge.
To do this, stop building and backfilling when the wall is about 8 inches (20.3 centimeters) from the top of the soil slope. Lay down a length of landscape fabric over the top of the aggregate (this will allow water to pass through, but not soil), then continue building the wall. Backfill over the fabric with soil. Whatever method you choose, the wall should reach about 4 inches (10 centimeters) above the backfill when finished.
- Remember, retaining walls aren't just for battling erosion. They also work well for creating gardening terraces, planting beds, or just for pure aesthetics.