Building regulations change. Building regulations vary from country to country and county to county. Always check. PT provides information to do the job; not to follow government regulations. This information also assumes that your building materials adhere to Australian standards. Countries like China are notorious for not having quality controls and for cheating on standards. (Remember Sanlu milk that killed babies ?)
|
Footings
Concrete Precast concrete Drains Brickwork Concrete blockwork |
UNFINISHED |
The length of life of most building materials is determined by the resistance to frost. In the UK climate with 4 months a year having intermittent rain, freeze, thaw, the conditions are very severe. The art of good building is to select the right materials for the right results.
All foundations should be excavated down to a solid bottom where the bearing acpacity of the ground is over 107 and under 428kN/m2 safe load. The depth should not be less than 450mm. Excavation in clay should always be taken below the frost line.
A concrete strip foundation should be about 2x the width of the wall it supports, at least 150mm thick, preferably 225mm, and should extend beyond a point taken 45o down from the base of the wall in both directions. On soils of low-bearing capacity, both dimensions may have to be increased and the concrete reinforced as well.
[Pardon me if I disagree with the 'experts'. On clay, because it expands when absorbing water and shrinks when drying, the foundations should be at least 450mm thick with steel reinforcement; but thicker is better. Anything less than 400mm will crack under big seasonal differences in rain. In the UK in 1976 the drought caused massive damage to foundations of stately homes. In Hobart, a friend bought an older and quality solid brick home, which had never used guttering for the roof. When he installed guttering to carry away the rain, the clay shrank and the walls developed massive cracks that you could slip your hand through. These cracks would come and go with the rains.]
The following table shows safe loads for different soil-types.
| Nature of ground | Safe load kN/m2 |
|---|---|
| Natural bed of silt, peat, recent made ground | 27 |
| Alluvial soil, very wet sand, made ground well compacted, or tipped several years | 32-53 |
| Natural bed of soft clay, wet sand | 53-107 |
| Natural bed of fairly dry clay, fine dry sand or loam | 214 |
| Natural bed of dry, firm clay, boulder clay and natural gravel | 321 |
| Compact sand or gravel, hand boulder clay in deep foundation | 428 |
| Hard sandstone, limestone, chalk | 535-1070 |
On fens or made ground, reinforced concrete raft foundations laid on top of the ground and extending well beyond the limits of the building are essential. Work of this kind should be undertaken by civil engineering contractors as the quality of the concrete and the positioning of steel reinforcement are most important. It cannot be carried out by a small local builder or farm labor.
In shrinkable clays, foundations should be taken down to a depth of not less than 1.7m, otherwise they fracture during drought. To avoid the expense of deep foundations a hand operated or machine operated post hole auger, not less than 250mm diameter and preferably 300mm diameter, can be used for making holes 1.8m deep at about 1.4 centers along the walls. The holes are filled immediately with concrete and ordinary strip foundations laid on top about 450-600mm below ground level. The method is cheap, simple and can be carried out by a local builder or farm labor.
Large areas of concrete for floors, roads and cattle yards should be provided with expansion joints, at not more than 4.5m lengths in any direction. :
[There is a very large section on concrete on this website Core >> Craft & trade >> Concrete, bricks, stone. This section is merely a basic introduction for those builders in a hurry.]
Concrete is composed of Portland cement, aggregate and sand. Aggregate can consist of crushed gravel, broken stone or brick.Sand is just a fine aggregate which fills the voids between cement paste and large aggregate.
Premixed concrete can be obtained from specialist firms.
Aggregates described as as dug or all in should not be used. Sand must be clean, sharp and free from vegetable matter, loam and clay. Both must be dry for volume meazurements.
Water for concrete must never be from ditches, streams or rivers. Only clean water should be used.
To make good concrete the aggregate should contain particles ranging in size from the smallest to the largest. Mixes are generally described in terms of the proportion of cement, coarse aggregate and sand which they contain, and meazured by volume. The strength of concrete depends upon the relative proportions of water and cement- the higher the proportion of water in the mix, the weaker the concrete. Insufficient water also reduces the strength.All aggregates contain water, making it easy to include excessive water. The commonest fault in concrete making is excess water, so there is a test to determine its effect, called the slump test.
Rough slump test:
Pre-mixed concrete often arrives onto the site far too wet, because the truckie adds water on the way to make it easy to wash the mixer out after delivery. Write the slump test into your contract.
Concrete mixing by hand should be done on a clean wooden platform, turning over 2x dry and 2x wet. [Pardon my comment: This is very poor mixing. I turn and stir the dry mix until there is no streakiness, and this takes at least 6 complete inversions of the whole mix. Then I add water, allow time to soak into the cement dust, mix the water in thoroughly and then tumble for at least another 6 inversions of the whole mix.]
A machine mixer makes better concrete but must mix for at least 2 minutes. [For me that is too brief, for cement dust needs time to absorb the water; otherwise the water might not be evenly distributed, and some cement will have too much while other parts have too little.] If your concrete is to last 2000 years, why not spend 5, instead of 2 minutes, making it ?
Notes:
| Purpose | Cement | Sand | Aggregate |
|---|---|---|---|
|
1 1 1 |
3-3.5 2.5 " |
6 of size 20-45mm 4 of size 6-38mm " " " " |
| Mix | Cement | Sand | Aggregate | Water | ||
|---|---|---|---|---|---|---|
| kg | m3 | kg | m3 | kg | litres/kg | |
| 1 : 2 : 4 1 : 3 : 6 |
310 225 |
0.43 0.47 |
660 730 |
0.86 0.94 |
1240 1350 |
155 ** 113 ** |
The volumes are only approximate.
** A water/cement ratio of 0.5 weight for weight (not volume) was used for a rough guide so you have enough water on site. The manufacturer's guidelines must be followed for the exact quantity of water to pass the slump test. [1 litre of water has a mass of 1 kg.]
During frosty weather, newly laid concrete must be protected with straw or bags, and concreting should cease when the temperature falls below 4oC. In hot weather the surface of newly laid concrete should be kept damp by means of vinyl/PVC sheets, wet bags, tarpaulin or straw.
Agriculture is well supplied with precast concrete building products: mangers, water troughs, fencing posts, building blocks, portal frames, pipes, prestressed beams and paving slabs. The concrete is made under laboratory conditions and the steel accurately placed into olds. Local farm labor or builder cannot achieve the same results.
Loft floors can be economically built in reinforced concrete or precast concrete beams or prestressed precast beams. The latter are often cheaper than timber for certain spans and also more hygienic. The manufacturers should be consulted for theri range of products and pricing.
This section is mainly for the UK but has helpful information mixed in.
Pipes:
Drains should have a velocity of 1.2m/s when flowing full. If the fall is too great the water runs away leaving the solids behind.
Pipes of 100 and 150mm diameter usually fulfil most requirements on the farm. Pitch fibre pipes are laid to minimum falls, say 1 in 80 for 100mm pipes.
Stoneware are laid according to this table.
| Diameter mm | Fall | Discharge when half-full litre/min |
|---|---|---|
| 100 150 225 300 |
1 in 40 1 in 60 1 in 90 1 in 120 |
280 670 1600 3000 |
Rainwater pipes need not discharge over gulleys, except where a connection is made into a public sewer. [In Australia, rainwater pipes must not drain into public sewers. This would overload the sewage treatment plant.] The ends of the pipe can be connected directly into the socket of a slow bend projecting about 75mm above the ground and the joint made in weak lime cement, sand and mortar 1 : 1 : 10 and painted over with tar. If a sleeve is fitted over the end of therainwater pipe, the joint can be broken, the sleee removed, and the drain rodded in case of blockage. It is cheaper than a gulley, which blocks with straw and litter, though some farmers prefer th elatter in all normal situations away from strawed yards. Gulleys with circular outlets and gratings are easier to clean than rectangular ones.
Brickwork:
Usually blockwork is cheaper than brickwork, and more suitable for farm walling. Most precast blocks are about 450 x 225mm and of various thicknesses between 75 and 225mm, solid or hollow, dnese or lightweight concrete. It is important to distinguish between structural and insulating blocks and those used for insulation but capableof being loadbearing.
In Australia, the usual nominal size is 400 x 200mm, the actual size is that minus the thickness of mortar; but there are variations; also block widths vary: 90, 150, 140 and 190mm.
Dense aggregate blocks may be solid or hollow, the former mainly used for up to 150mm thickness, the latter, depending on function, for 150-225mm work since solid blocks of these thicknesses are heavy to handle.
For retaining walls and cattle yards, the hollows permit vertical bars of steel reinforcement, making the walls much stronger than brickwork, and can be filled with a concrete grout, well tamped with a timber batten every second course.
Blocks suitable for cross wall construction can be solid, or sometines hollow with a minimum thickness of 75mm. Aerated concrete blocks are excellent insulation for internal walls, having a sponge-like texture which is easily worked or nailed.
Mortar should not be stronger than 1 : 1 : 6 (cement : lime : sand) and 1 : 4 below ground. With hollow blocks, the mortar bed must cover the solids. Excessive height and length of walls can make them unstable. This table gives the maximum dimensions that should be used.
| Block thickness, mm | 50 | 62 | 75 | 100 | 150 | 215 |
|---|---|---|---|---|---|---|
| Maximum length & height of wall (supported at top) (metres) |
2.5 | 3.0 | 3.6 | 4.5 | 6.0 | 7.6 |