Roads
Contents
Farm roads
Within a farm there are usually 3 types of roads, with each serving a different purpose and therefore needing different treatment:
- access road connecting farmstead to highway
This artery of the farm needs not only a good layout but a reasonably good surface. The width should not be less than 3m to prevent concentrated wear and to allow for wide vehicles. If the 'highway' is narrow and the incoming trucks 2.4m wide and long, then the access might need to be considerably bigger. Passing bays should be provided at not more than 150m intervals.

Farm access
Vehicles might include grain merchants' lorries, bulk milk tankers and machinery delivery. The typical entry is splayed but a bell-shaped entrance is recommended for large vehicles, by the Road Haulage Association. High livestock-carrying vehicles must be allowed for, and in grain storage areas tipping bodies take extra height. A tipped articulated vehicle may reach over 10.5m. The clear height above main farm entrances and main farm roads should be 5m, the design standard of the Dept of Transport. Unless a particular need is recognized for extra clearance, the rest of the area should allow at least 4m.
| Notes | a | b | c | d |
a = highway width available to vehicle (metres)
b = width of road entrance
d = width of gateway
c = distance between road and gateway.
|
3 6 9 |
9 7.5 6 |
9 7.5 6 |
4.25 4.25 4.25 |
The weight of traffic on a farm road is light, weight being the frequency of traffic, not wheel loads, because a light 4-wheel lorry sometimes has a greater wheel load than a heavy 6-wheel vehicle.
What wears out a road is speed plus weight, and therefore speed should be restricted. Bulk tankers for grain or milk can be greater than 20 t. Steep gradients should have concrete 'grips' to assist wheels.
- roads linking buildings
Roadways around buildings vary in width in proportion to the amount of traffic discharging them. They should be laid clear of the buildings, except where they serve as links. Large vehicles entering a cul-de-sac need space to turn, so all bends and turning circles should not be less than 16m.
- internal roads linking fields
Internal roads usually serve to link fields and buildings and take mostly tractors, trailers and stock.
Back to Contents
Constructing roads
To keep the cost down, use local materials: chalk, quarry waste, ashes, hardcore from old buildings, flints, burnt shale, limestone chatter. The finished surface can then be treated with a coat of tar or bitumen to keep water out of the subsoil, but this will not form a hard-wearing surface.
Keeping the subsoil dry is the art of successful roadmaking. Therefore never excavate into the ground to make a road, although vegetable soils must be removed, but build up from the ground surface.
On sloping sites, a land drain on the rising gradient side of the road should be provided. All work should be done in dry weather, preferably during the summer months.
The junction with the highway must be carried out to the satisfaction of the county council, possibly in pre-coated stone laid on a suitable stone base. It might be possible to have this done by a highway authority when a roadmaking gang are working in the area (but it won't be cheap). An existing farm road can be given a wearing surface of pre-coated stone laid between 50-75mm thick and then well rolled. The work should be completed while the material is still warm. Alternatively, uncoated aggregate can be laid first and grouted afterwards with tar or bitumen. If the surface is good, it merely needs surfacing with a coating of bitumen or tar applied through a watering can and covered over afterwards. All sharp bends should be constructed in concrete as the greatest amount of wear occurs on corners.
Wheel track roads in concrete cost almost as much as a full width road, owing to th elabor required in forming the track. Concrete should be 150mm thick on at least 150mm compacted hardcore, with mesh reinforcement when bulk tankers, etc, use the road.
Internal roads around buildings should be constructed in 1 : 2 : 3 concrete 100mm thick, laid on at least 100mm compacted hardcore after the vegetable material has been removed.
Reinforcement is only necessary in soil of low-bearing capacity such as peat, fenland silt, and the like.Expansion joints are necessary every 5m length of road, and the best way is to lay alternate 5m slabs, then return to pour the intervening slabs, obviating the need forexpansion strips of wood or fibre boards. When laid the concrete should be cured properly.
(See Craft & trade >> Concrete >> Concrete theory >> Curing)
To save expense, passing bays can be constructed of hardcore; 2.5m wide by 12m long.
Light internal roads are made by laying 100-150mm hardcore or pitching on top of the surface of the vegetation, after it has been well rolled. The larger stones are laid at the side, the smaller in the center, and the surface is covered with ashes. A furrow slice should be turned up along the sides to hold it together and wet spots drained and then consolidated.
Crawler (track-laying) and spade lug wheel tractors should be kept off farm roads. Hooves and manure, whilst destructive to bituminous and tar roads, do not affect concrete.
Many farms need a weigh bridge. This should be sited with adequate access to both ends, peferably near the farm office, and a by-pass provided. The manufacturers should be consulted as to size.
Back to Contents
Bridges, culverts
Where ditches have to be crossed, a bridge can be formed from pre-cast concrete pipe. The 'invert' or bottom of the pipe should be laid about 150mm above the natural bed of the ditch. Placing the pipe below the bed reduces the effective diameter of the pipe if it settles, and again when silting up, as it invariably does, thereby restricting the flow of water. Oil drums, with the ends knocked out, laid end to end and surrounded by concrete, are an alternative to pipes.
Spans of up to 6m can be effectively and economically bridged by pre-stressed standard type concrete beams, laid on a mass concrete abutment, or on a suitable concrete base laid on either side of the banks.
Unit beams vary in size and shape according to manufacturer, but 225mm wide by 150mm deep is an average; they can be laid with farm labor, and are often cheaper and certainly better than railway sleepers.
Back to Contents
Cattle grids
The time saves in opening and closing gates soon pays for a cattle grid. Siting and construction needs careful consideration, otherwise an owner may find himself liable to damages in case of accident or injury, expecially if there is a right-of-way over the road.
The grid must be stockproof to contain cattle, horses and pigs; it should be at least 2.6m long, 3m for sheep, the width being the width of the road.
Types of cattle grid:
- Manufactured:
- a metal frame hinged in the middle in the form of an inverted V and supported by 2 springs attached to the top of the gate post. When a vehicle contacts the frame, it flattens out and is run over, the springs returning it to the original position when the vehicle has passed over.
- V-shaped precast beams set together in the form of a saw tooth on a concrete slab at ground level. This is difficult to keep clean and soon fills up with mud.
- Home-made:
the one usually found on farms, consists either of steel joists (if heavy loads are to be carried) or of 50mm diameter mild steel tubes at 175mm centers, fastened to railway sleepers set on edge, or on dwarf walls to 450mm depth with concrete capping. The 2 top edges of the sleepers are chamfered off with an axe and V-shaped notches cut, into which the tubes are fitted for half their diameter, the other half standing proud. Three sleepers at 300mm centers support the tubes under each wheel and there is an additional one in the center. The sleepers in turn are supported, either by 3 other sleepers at right-angles to them or by precast concrete blocks, the total depth of the pit over which they are being laid being about 450-500mm. The bottom should not be concreted unless there is a catchpit and drain.
The grid should be fenced off along its length leaving a clearance for overhanging loads. A 4.5m by-pass gate for farm machinery to pass through should also be provided. At least 1.5m should be left between the gate and the grid, or driven stock may be forced onto the grid.
Back to Contents