Concreting - part 1

Contents

Part 1
Intro
1: Checklist
2: Plan
3: Buying materials
4: Site preparation
5: Underground plumbing
6: Fixing formwork
Part 2
7: Termite protection
8: Reo, steel reinforcement
9: Stepped footings
10: Mixing concrete
11: Laying & levelling
12: Finishing touches
13: Curing concrete

Intro

This chapter is extensive. You might prefer to use a briefer chapter from the Concrete & Brick section, or the Home Handyman section.

Concrete is one of the easiest building materials to work with. The techniques for laying anything from a garden path to a house slab, are much the same, once you know the basic rules for: The rest of this chapter is for the serious builder, and can be skipped by the DIY concreter of patios and paths.

1: Checklist

Materials checklist:
Back to Contents

2: plan

  • Order your concrete days in advance and allow time to have formwork finished and helpers ready before delivery. If the day will be hot, arrange an early delivery. Do not pour if there might be frost. When you place the order arrange to phone to confirm on the day, a couple of hours before the specified delivery time. If your preparation is delayed and the truck arrives on time, you are in deep trouble.
  • For some jobs, the local council's planning department will insist on inspecting the site before your pour concrete. If you fail to do this, the council can insist that you remove the concrete. These arrangements take time, perhaps 2 months if approval of your plans are required, so speak to the council early to put in the paperwork.
  • Back to Contents

    3: buying materials

    Concrete is made by mixing:
    There are 3 ways to do it:
    Different projects require different thicknesses of concrete and the mix must be adjusted accordingly. Basically, the greater the load on the slab, the thicker it must be. Here are the most common mixes:
    To calculate the volume of cement and aggregates needed for a rectangular slab or trench:
    volume = length x width x thickness
    Keep all meazurements in metres; to get metres, divide mm by 1000, cm by 100)

    Your computer has a calculator to help you.
    To find your calculator you usually go to the Status Bar at the bottom of this screen:
    Start => All programs => Accessories => Calculator.

    Allow for wastage either by rounding up volumes to the nearest half or whole cubic metre, or by adding 5%. You will tend to use more cement than your calculation suggests, so allow for this.

    Crushed rock comes in different sizes, with the maximum size specified. Some suppliers are unreliable and will dump over-sized aggregate on your site and drive off before you realize the mistake. I prefer a maximum of 19mm with a range of sizes, such that, with sharp sand added, everything compacts down to a solid mix, leaving no room for air.

    If you wanted a pretty ground finish to your concrete, you would need smaller crushed rock, perhaps FCR (Fine Crushed Rock). This would change the cement/sand/rock ratio, to use more cement since the surface area of crushed rock would increase. For strength and to reduce cost, I would lay a 25mm veneer of this on top of a normal (1:2:4) slab. Contact an expert for advice.
    Back to Contents

    4: site preparation

    One of the main factors that determines the type of concrete slab or the size of its beams and reinforcement is the foundation (ground) that the building is to be built on.
    The words footing and foundation are often confused. The footing is the lowest part of the building, and sits on the ground. The foundation is the ground under the footing. The footing transmits the load of the building to the foundation. As such, the footing includes the slab. The foundation supports or carries the building.

    A foundation classification for a building site is generally determined by a geotechnical engineer who will usually classify the site in a written report, based on the core samples taken from the drilling of the site . Also taken into account is the history of the site such as adjacent landslips, mining, large tree removal, the history of similar footing in the area ?

    Australian standard 2870/1996, allocates different classifications to the various foundation types found in Australia, in particular. It provides details and designs for reactive clay sites which can cause damage to buildings by swelling and shrinking under different moisture conditions. The Australian Standard soil classifications are:
    Site preparation:
    Back to Contents

    5: Underground plumbing

    Before any formwork for the slab is constructed the plumber must install the underground plumbing. He needs the outline of the construction set out on the ground. Once the plumbing is in, changing the outline might need a recall of the plumber which would be expensive. So double-check the outline before the plumber arrives.
    All pipes should be taped up to prevent concrete getting in them.

    Do any power lines need to come up through the slab, such as for an island kitchen bench or home cinema requirements ? If so, the electrician may need the plumber to lay the pipes.
    Back to Contents