7: Termite protection

In the areas with termites, termite barriers are necessary. Such barriers include:
All of the above termite barrier systems are installed by fully qualified specialists for each system, and it is vital to know when to call them during the building construction process. The concrete slab itself, if constructed to the requirements of the Australian Building Standards, is considered to be an adequate physical barrier against termites. (However if the slab cracks under a timber wall, the termites can enter, hidden, with devastating results.) Any penetrations through the slab, such as plumbing pipes, as well as the perimeter of the slab, must be protected from termite access.
Back to Contents

Step 8: Reo, steel reinforcement

Reo, that is, steel reinforcement in the form of rods or a mesh, should be included in the slab in areas of stress. 5mm mesh is all that is required for most home projects but mesh for parts of a house will be specified on the council-approved house plans.

Reo must have sufficient concrete around it to prevent moisture reaching it, causing it to rust. This amount of concrete around the reinforcement is knowing as cover. If the reo rusts it can cause the concrete to spall, known as concrete cancer, and lose strength.

If you have to cut the concrete and thereby expose reo, paint epoxy or rustproof paint on the reo to prevent rust.

The minimum cover required is:
Cut the reo to shape using bulk cutters or an angle grinder. Put the reo in place sitting on plastic stands called bar chairs. These will keep the reo off the ground with the correct cover.

Placement of reo

Both the top and bottom rows of reo should be cut to size, allowing a full lap at corners and T intersections section. Where mesh or rods overlap, they should be wired together. The reinforcement must be held clear of the trench bottom and sides by sufficient distance to provide the correct concrete cover. This positioning is achieved by using bar chairs or trench mesh supports.

Service penetration

When pipes and conduit pass through strip footings: Seek the advice of your architect or engineer.

Any pipes that pass through the footing should be wrapped with a foam lagging or a rubber sleeved to allow for the movement and prevent damage to the pipes.

The same principle applies for rock outcrops interrupting part of a footing. Extra reo may be added around the obstruction.
Back to Contents

9: Stepped footings

These images look feint and tiny. To read them easily, enlarge by holding [CTRL] + clicking [+/=] many times.

Stepping of footing
The base of a strip footing shall be: When stepped, the footing will use one of the methods in these diagrams. The specific details are given in these paragraphs below.

The top of the footing still needs to be level and stepped. The height of the steps ideally should suit brick courses to minimize any brick cutting when laying the base brickwork.
Steep slopes will require the bottom of the trench to be stepped. See the diagrams below. Steps in the footing can usually be formed using a couple of bricks placed during levelling off.
Use a laser level and steel height pegs to set the top of the strip footing and where any steps should finish in the trench.

trench+mesh.gifTrench mesh:
Bars:
For both mesh and bars, cover to the reinforcement shall be 40 mm.

Service penetration shall be permitted through the middle third of the footing. Footing penetrations in the top or bottom thirds shall require extra depth of footing or extra reinforcement.

The concrete shall be not less than N20mpa with 20 mm nominal maximum aggregate size. Slump shall be selected to suit the construction conditions.
foot_step01.gif

foot_step02.gif

foot_step03.gif

foot_step04.gif
Back to Contents

10: Mixing the concrete

At this stage, you should also consider adding a colouring agent to your mix. Liquid and powder forms are available in a range of earthy colours to highlight the overall design of your path or driveway.

There are 3 methods for getting your concrete: